Elizabeth Street Water Main Renewal

  • Project typeAsset Refurbishment
  • Project value$399,619.87
  • Project scheduleProject Start: October 5th 2021 - Approx 9th November 2021 (pending weather)
  • Contractor nameKillards Infrastructure Pty Ltd
  • Completion Date09 November 2021
Elizabeth Street Moss Vale

Wingecarribee Shire Council has improvements planned for Elizabeth Street in Moss Vale which will be completed two stages between the Kirkham Street and Valetta Street roundabouts.

  • STAGE 1: replacing the ageing water mains on Elizabeth Street.
  • STAGE 2: road re-surfacing as part of the 2021/22 Capital Works Program.

When complete this project will provide an improved roadway and attractive streetscape, while also renewing the water supply infrastructure to properties in the area. There will be temporary interruptions to your water supply during construction, however these will be kept to a minimum. As part of the project, all trees on the western side of Elizabeth Street will remain in place and not be removed.

Stage 1 is planned to commence on 5 October and replacement of the water main will take approximately five weeks to complete.

The construction in Stage 1 will require works in the street nature strip which may occasionally cause inconvenience for pedestrians, property owners, motorists and residents. Traffic control will be in place whenever required, and property access will be maintained in consultation with residents.

Our contractors, Killard Infrastructure Pty Ltd, will need to access approximately 60m of the road, car park and footpath area. Traffic controllers will be on site during work hours to assist pedestrians and traffic navigate the work zone. 

Construction works hours are from 7 am to 5.30 pm weekdays, and 8 am to 1 pm Saturday.  

Please contact us on phone 4868 0888 to discuss your property, or provide contact details for works notification.

Location

Elizabeth Street, Moss Vale 2577  View Map

Google Map