Aquatic Centre Construction

The Moss Vale War Memorial Aquatic Centre opened to the public on Saturday 30 November 2013 and will be operated by Belgravia Leisure. For the full list of fees and charges please click on the link below.

Moss Vale War Memorial Aquatic Centre Fees and Charges 2013/14


Check out the aquatic centre website at www.mvaquatic.com.au Enquiries about classes and membership can be made via email to enquiries@mvaquatic.com.au or call 4868 1967.

 

For regular updates on what is happening at the centre, check out the Facebook page.

 

 







 

Facilities

 

AQUATIC CENTRE PROGRESS

 

PROJECT UPDATES were prepared to keep residents up to date with Aquatic Centre construction and associated activities during 2013. Download a copy below:


 Aquatic Centre Update newsletter_January 2013


Activity schedules, financial information, project milestones and more is included in construction reports provided below:


March 2013 PROJECT REPORT (875KB PDF)
February 2013 PROJECT REPORT (PDF)

November 2012 PROJECT REPORT (PDF)

December 2012 and January 2013 PROJECT REPORT (738KB PDF)


Scroll down the page to see a photographic summary of construction progress.


29 October 2013

While the centre looks like it is almost complete there are still many small jobs to finalise before opening to the public.




















6 September 2013
Belgravia Leisure has officially been appointed as contract manager of the indoor Moss Vale War Memorial Aquatic Centre.


Council awarded the contract for operation of the $8.4 million facility after councillors selected Belgravia Leisure as the successful tenderer at the Council meeting on 10 July, 2013. Click here to read the full media release.


Painting collage
















Painting and tile grouting are well underway.

Grouting the tiles in the pools


























26 July 2013The footpath area is now complete directly in front of the aquatic centre and the parking lane re-opened. Work continues on the carpark in this area as well as in front of Community Oval further up the road.








Reception desk area is nice and bright. 3 lanes complete in the pool - squint to see the progress made on rooms along pool side.


Pool tiling in progress.



Gym is almost complete. A very large space!





28 June 2013


Walls are going up around the building. The entrance, office, gym, creche and canteen areas are now completely enclosed. Pool construction continues, including ramp access. Tiered seating is also being built.

Entry including ramp




















16 May 2013

The main office and gym area area have now been enclosed and the main pool is full as it is checked to ensure it holds water.































15 April 2013

Steady progress is being made. Check out our Facebook page for more regular updates.




















































11 March 2013

It's a hive of activity on site today as a start is made on steel reinforcing for the floor of the main pool, gym and admin areas. Note the roof is now in place.










6 February 2013

Rain has delayed work on the ground but the roof continues to take form. Underground electrical and sewer work is underway.

Panorama photo of site taken 6 February 2013


10 December 2012

The building is quickly taking shape with steelwork anticipated to be 90% complete by Christmas.

 

  

6 December 2012

Media release issued regarding subsidies announced for Moss Vale area residents while the aquatic centre is constructed.

 

5 December 2012

The first pylons are going up today!

  

28 November 2012

Report considered by Council regarding travel subsidy for schools and residents. Click here to view the report and minutes.

 

21 November 2012

Drilling started today for the foundation piers.

Work on foundation piers commences

 

 

23 October 2012

The first load of steel arrived on site today.

 

 

20 September 2012

The image below shows the Moss Vale Pool site on the first and last days of demolition works. Same view. Demolition is now complete.

Before and after demolition

 


3 September 2012

Having excavated all pools and removed rubble from the site, workers have started backfilling the hole where the deep end of the pool used to be. This serves two purposes:

  • To provide a safer site by reducing the potential for anything to fall into what was recently a 4m deep hole.
  • To bring ground levels up to that required for the building works.

 

 


24 August 2012

What a busy week on site. By mid afternoon today there was nothing but sand left of the pools. 66 truck loads of rubble were removed over 3 days to the Resource Recovery Centre this week.

 


 

 

20 August 2012


 

The main, todder and baby pools have all been demolished.

 

 


13 August 2012

 

Temporary fencing around the perimeter and site sheds were set up last week. Electrical and water services for construction were also connected to the site.

 

 Temporary fencing and site sheds image


Holes were punched into the floor of pools as part of concrete testing. This allowed contractors to see whether it was safe to have heavy machinery working within the pools.

 

Concrete testing image

Demolition of existing buildings and pools commenced in earnest today.

 

Demolishing pool coverings and shelter shed

 



WHAT WILL THE CENTRE LOOK LIKE?

Still images and a digital walk through of the new Moss Vale Aquatic Centre are shown below.

 



Moss Vale Aquatic Centre Entry


























Moss Vale Aquatic Centre - Entry


Moss Vale Aquatic Centre Pool Hall #1














Pool Hall


Moss Vale Aquatic Centre Pool Hall #2














Pool Hall


Moss Vale Aquatic Centre Pool Hall #3













Pool Hall


Moss Vale Aquatic Centre Pool Hall #4




















Pool Hall

Last Updated: June 1st, 2017